| 2009 |
Caltrans Vernal Pools and Habitat Restoration |
|
| |
$417,150.00
Construction of over 160 acres of created and restored vernal pools
Caltrans Division of the State of California
District 6
Hwy 41, Madera Co., CA |
| |
|
|
| 2009 |
KCWA Section 4 Recharge Facility |
|
| |
$928,199.00
Kern County Water Agency
Dee Jasper & Associates Engineering- Curtis Skaggs, Engineer
Furnish and Complete Pump Station and Discharge Piping
Bakersfield, CA
|
| |
|
|
| 2009 |
Columbia Canal Company |
|
| |
Randy Houk, General Manager
Levee Restoration on the San Joaquin River
Mendota, CA
|
| |
|
|
| 2008 |
Firebaugh WWTP |
|
| |
$3.1 Million
Jose Ramirez, Firebaugh City Manager
Jimmy Dang, Engineer
Kennedy and Jenks Consultants, San Francisco, CA
Construction of five lift stations, expansion of existing waste water facility
Firebaugh, CA |
| |
|
|
| 2008 |
Santa Nella WWTP |
|
| |
$1.4 Million
Mark Reitz, Engineer, Boyle Engineering, Fresno, CA
Rough grading for WWTP and Water Treatment Plant
Santa Nella, CA
|
| |
|
|
| 2006 |
Mendota WWTP Expansion |
|
| |
$400,000.00
Giersh and Associates
Pond excavation and storage
Mendota, CA |
| |
:: top :: |
|
| 2006 |
Don Pedro WWTP |
|
| |
$2.6 Million
Dick Anderson Construction, Bozeman, MT
New construction of WWTP
Lake Don Pedro, Mariposa County, CA |
| |
|
|
| 2006 |
Armona WWTP |
|
| |
$750,000.00
John Hernandez, Provost and Pritchard
Reconstruction and expansion of WWTP
Armona, CA |
| |
|
|
| 2005 |
Huron WWTP |
|
| |
$3.3 Million
Mike Giersch and Ray Martinez, Giersch and Associates
Reconstruction and expansion of WWTP
Huron, CA |
| |
|
|
| 2007 |
Los Banos Pedestrian Bridge |
|
| |
$294,000.00
Gary Hutsell, City of Los Banos Department of Public Works
Mario Gouveia, Engineer, Boyle Engineering, Fresno, CA
Site development and construction of new pedestrian bridge
Los Banos, CA |
|
|
| 2004 |
CCID Canal Bypass and Water Control Structures |
|
| |
$2.4 Million
Mario B. Gouveia, Engineer, Stoddard and Associates
Central California Irrigation District, Russell Landon
Canal bypass construction and new weir installation
Los Banos, CA |
| |
|
|
| 2006 |
City of Kerman |
|
| |
$600,000.00
Yamambe and Horn Engineering
Install new 1 million gallon municipal water storage tank
Kerman, CA |
| |
|
|
| 2005 |
Central Unified Daren Koligian Stadium |
|
| |
$1.35 Million
Micham Inc., Bobby Tracy
IOR Inspector Steve Folley
Excavation, grading and paving
Fresno, CA |
| |
|
|
| 2008 |
Maldonado Skate Park |
|
| |
$767,000
Jose Ramirez, Firebaugh City Manager
Alison Hobbs, Project Manager, SSA Landscape Architects, Santa Cruz, CA
Construction of Skate Park
Firebaugh, CA |
| |
|
|
| 2008 |
Maldonado Park |
|
| |
$2.1 Million
Alison Hobbs, Project Manager, SSA Landscape Architects, Santa Cruz, CA
Construction of City Park
Firebaugh, CA |
| |
|
|
| 2004 |
Mendota WWTP |
|
| |
$750,000.00
Mike Giersch and Ray Martinez, Giersch and Associates
Reconstruction and expansion of WWTP
Mendota, CA |
| |
|
|
| 2008 |
Landmark Irrigation |
|
| |
$128,000.00
Fred Treat, Project Manager
Construction of eight holding ponds
Various locations through out the Central Valley |
| |
|
|
| 2007 |
Spreckles Sugar |
|
| |
$172,000.00
Tom Pritchett, Plant Manager
Construction of waste water storage facility
Mendota,CA |
| |
|
|
| 2007 |
City of Merced Well Site 16 Improvements |
|
| |
$737,000.00
Installation of equipment, earthwork, grading and paving
Merced, CA |
| |
|
|
| 2008 |
Greenhills Elementary |
|
| |
$620,000.00
Bush Construction, Hanford, CA
Pads, grading, asphalt, parking lots, striping
Chowchilla, CA |
| |
|
|
| 2008 |
Ellis Elementary |
|
| |
$1.2 Million
Micham Inc., Woodlake, CA
Pads, grading, asphalt, parking lots, striping
Madera, CA |
| |
|
|
| 2005 |
Mollie Bakman Elementary |
|
| |
$400,000.00
Mauldin Dorphmier Construction, Fresno, CA
Excavation, grading and paving
Fresno, CA |
| |
|
|
| 2008 |
Woolf Enterprises |
|
| |
$84,500.00
Airport repair
Huron, CA |
| |
|
|
| 2008 |
Peri Brothers |
|
| |
$313,000.00
Tiny Morris, Owner, Morris General Contracting, Kerman, CA
Grading for parking facility, loading dock to main building
Firebaugh, CA |
| |
|
|
| 2006 |
Driscolls Fruit Packing |
|
| |
$371,000.00
Earthwork
Ballico, CA |
| |
|
|
| 2005 |
City of Fresno Fire Stations 15 and 17 |
|
| |
$250,000.00
L.C. Nelson Construction, Selma, CA
City of Fresno, Mark Johnson , Project Manager
Excavation, grading and paving
Fresno, CA |
| |
|
|
| |
Henry Miller Reclamation District |
|
| |
154,000.00
Central Regulating Reservoir
Summers Engineering, Inc. Hanford, CA
Scott Jacobson
Henry Miller Reclamation District, Dos Palos CA |
| |
|
|
|
|